Vinci – Circle Reading

We have just completed our 16th week on site and the contract is going well. 2nd fix has been completed on the Ground Floor with Tapers lined up for next week. 1st fix has been completed on both the 1st & 2nd Floors and we have started 1st fix on the 3rd floor. The plant room has been completed to enable M&E to complete their works and the atrium area has been boarded.
We are in the process of installing the lead lined board to the x ray rooms and in discussions with Vinci on the SAS ceiling systems which are to be installed.
Please see our progress photos below;