Balfour Beatty, Cowlin Construction – St Marys School, August progress

Progress on St Marys School is going well and 90% of the hardwall on site has now been completed and the gyptone ceiling to the sports hall is currently being taped. We have recently secured the suspended ceiling pakage which will commence over the next couple of weeks, once we have completed curved bulkheads to corridors and M&E have completed their works above ceilings.
Please see our progress photos below