Bam Construction – Robert Blake & Elmwood School, Bridgwater

In early April we commenced work on Robert Blake & Elmwood School for BAM Construction. Our work comprises of approximately 3000m2 of Metsec framing and Aquaboard sheathing to the external envelope of the building. There is 13 weeks work comprising of 3 visits in an overall period of 38 weeks. The first zone is in progress and due for completion this week.
Please see our progress photos below