Vinci Construction – Mountain Ash, approaching completion

Mountain Ash is reaching 90% completion with the main focus now being on ceilings and the internal atrium which involves bulkhead details and recessed lighting features.
The corridor ceilings are a mix of MF margins and an SAS trapezoidal suspended ceiling tile which will be installed to follow the curvature of the partition walls.
One of the last areas to be completed will be the x-ray room which uses lead-lined plasterboard and lead-lined plywood.
The aim for project completion is June 2011.
Please see our progress photos below