Leadbitter – M32 Junction 3, Bristol

As completion of the project approaches for Main Contractor Leadbitter and with our works almost complete in the 53no apartments and 6no town houses, the areas which are now being prioritised are the staircases, learning resource centre and commercial units. On the ground floor of the learning resource centre the mass barrier ceiling has now been completed, this has released the works to the floating rafts which is expected to commence imminently’.